CTA’s Commissioning team provided services for the new First Interstate Bank in Helena, which included verification that proper start-up was performed on mechanical systems including boilers, condensing units, air handlers and data room air conditioners. Functional performance tests were completed on all mechanical systems to ensure proper operation and efficiencies. CTA also verified a sampling of the test and balance process and total mechanical system operation was verified through testing of the web-based building automation system. Additionally, testing of the automated lighting systems and domestic hot water systems were completed to meet LEED requirements. A commissioning report was developed and documentation of the process was uploaded to LEED. Commissioning for this project was completed and met the LEED Fundamental Commissioning Requirements.